Friday, 7 May 2010

Transmission - Omneon

Even though we have been talking with Timeline about the possibility of getting an EVS from them to deal with playout I still felt that it would be use3ful to get the Omneon up and running as a backup. I connected the director to two media ports via firewire and then powered up the store. At this point I realised that I didn’t have the connector between the fibre channel connections on the Director and the 9 pin D-type connections on the store. After a fruitless search for this cable I emailed Omneon support using a link on their website.
 
 N-Store

Simon from Omneon support got back to me on the same day and has been incredibly useful helping to identify our system as a D1 (Director) with an NStore (Storage). However he also stated that “This is a very old unsupported system”, no surprises there, but it appeared that all we were missing was the connection cable which is hopefully being sent through as I write this.

 Director

Although we may not use the Omneon on the day we will certainly get the system up and running and ingest content onto it just to make sure that it still works. At the end of the day the EVS will have to be returned and while it is a viable work around I think we still need to be looking at re-integrating the Omneon with the Pharos control platform in the long term. Maybe this could be done next year as a side project integrating it with the mobile presentation racks.
 
Fibre Channel Connections

Tuesday, 6 April 2010

Engineering - Update

Seeing as all the engineering departments are now moving into TV systems to do their work we decided to have a massive tidy up. Not the most exciting of jobs but something that needed to be done none the less! We began by sorting through the piles of equipment and sorting it into different groups, transmission, audio, video etc. Then we created separate areas for all of these so that we would know where everything was when we needed to get to it.

Then we had the daunting task of sorting through and recoiling the cabling that was all over the floor, however with all of us helping out it didn't take that long before we had loads of need piles of video and audio cabling. 


After moving a few of the defunct racks about and re-positioning them at the back of TV Systems we then had a space in which we could place our newly created TX, OB and Interactive racks.


The last thing to do was to install a couple of internet connected PC's at the back of the room, a mega sound system and place a few tools here and there. As an afterthought we also obtained a white board and some engineeringesque posters to brighten the place up. TV Systems has now been affectionately been dubbed the "engineering office" and hopefully we'll be able to get a fair amount of Rave Live stuff done!

Transmission - Racking the Equipment

We have finally managed to find and sort out some half height mobile racks that we think will be suitable for the TX, Distribution and Presentation areas on the day of the event. Jamie has been busy drawing up system diagrams and working out what pieces of equipment would need to appear on the CTP's of each rack.

Meanwhile we racked the TX equipment (encoders, mux, IRD etc) into one of these racks in preparation. It got a bit fiddly in terms of leaving enough space so that everything could be cooled and so that each piece of equipment would be easily accessible from the back of the rack. In the end everything managed to fit and after plugging up and sorting out a few minor problems within the encoder configurations the rack was up and running again. 

 

Saturday, 3 April 2010

Engineering - Musion

On Wednesday Emily (Sponsorship & Branding), Kat (Branding), David (Talent Showdown Producer), Dave and I went up to Regents Park to visit Musion.

Musion are the world leaders in 3D holographic projection systems and what we saw during their demonstration was fairly incredible, the basic idea is that an HD image is projected onto a transparent foil which makes it appear as if it were floating in mid air. The image can then be interacted with by a rehearsed presenter providing a very realistic holographic feel to the set-up.

The idea for Rave Live would be to to have this holographic set-up on the main stage and use it to present channel listings and student animations, along hosting the initial opening to the event. There was also another idea to provide some kind of live 'telepresence' (making a person appear as a hologram) for which we would need to provide the camera.

Dave and I went along to view this from a more technical perspective and as such we were looking at the real-time implications behind using Musion on the day, as such we came up with a list of pros and cons:

Pros:
  • Looks really good when it is shot and filmed well
  • They will provide the equipment to achieve this and also the man power to rig it up
  • They will provide some help to us when filming and producing the content for this
  • They can do it with a feed of HDSDI which we can achieve with a HDX900 from stores
  • If we can include this in one of the shows as an insert then it will look really professional and engage the audience really well
Cons:
  • It needs a lot of light for it to work and also it needs a light show to be effective
  • The equipment that they will bring is heavy which will put some restrictions on our shows rigs due to weight
  • It will take 6+ hours to rig which eats into a whole days rigging time, assuming that we cannot rig around them on the stage so this cuts the stages rig time by a day
  • The screen is expensive and can be broken, with students on and off stage all the time there would be a possibility that it could get broken
  • It works best with high contrast meaning there should be as little light off the stage as possible. With the venue being used as an exhibition as well there will be a lot of light spilling onto the stage
  • We're not sure how this will fit into the schedule, with the shows on stage and the time needed for the turn around will there be time to show anything on this?
  • We do not have the content yet, it seems a little bit too late to be making content now
Obviously a lot of these points require us liaising with representatives from Musion, especially the items concerning the actual rig. The idea is to start doing this as soon as management have decided how they wish to proceed and whether or not we will actually be using Musion.

Wednesday, 17 March 2010

Interactive - Update

After speaking with Alex we have gathered a list of things completed and a list of things to do.

From last term here is what was achieved:
  • Installed the Red5 server, this streams to our flash pods.
  • Set up the proxy server for the trolley network, so that the internet can be accessed from one box.
  • We have a much better understanding of how the Red5 streaming service should work and how the flash application (pods interface) will play the streams.
  • The trolley has been racked correctly.
  • The server and client are also setup, with the server now running the DHCP service required.

Things that need to be done:
  • We need to either develop a server side application to the pods using one of the demos provided by Red5, an alternative would be to use Adobe's Flash Media Streaming Server, although we need to talk to sponsorship about this.
  • For the client side of this application, Max will need to come up with an interface that we can use to bridge the gap to provide the data that he required.
  • We need to set up the FCS workflow, James Uren said that he would help out with this in the first week back. All of the information to be used as metadata also needs to be gathered.
  • We need to run power to all of the equipment in the racks.
  • A live stream needs to be sent to Narrowstep via the Cisco media encoder, Max will need to re-skin the interface of the Narrowstep player to re-brand it to 2010 Rave Live.
  • Jon was having trouble configuring the net booting process, we also found out that the Dell towers we are using as the pods might not be able to net boot at all, this may simply be an upgrade of the BIOS or revert back to booting from the USB pens.
  • We need to work out the ports required.

There is still a lot of work to be done and we believe that the only way to break the back of this is to get the first years involved. This requires us sitting down and working out what roles they can fill. We also need to contact Max about getting access to the Media Bugs database and the Rave Live sign-up page on Media Bugs, this should preferably be done before we go back next week.

Engineering - Talent Showdown

Talent Showdown:
This is a pre-recorded programme (due to be shot on the 28th March) and the producers have asked for a hand with the flyaway and the rig. The plan is to build the flyaway at Coopers Technology College from which they can shoot their pre-recorded content, this will then be posted online for a viewer vote which dictates which "talent" will perfrom during Rave Live at Matter.
We accompanied them on a site visit last week to see what would be required. In order to minimise the fuss we are aiming to keep this as simple as possible, a basic 4 camera rig with a vision mixer, 2 VT Decks and monitoring. While on the site visit we drew up the rough system diagram shown below to give us a better idea of what we would need.


Several points arose during these initial planning stages:

  • We would need to provide an SPG to keep everything genlocked
  • The cable runs to the cameras were around 100m, this would have to be done over coax as the only cameras available were DSR500's and 570's, we now need to find out whether these are digital out or composite out, this would dictate the nature of the entire flyaway.
  • Would we take both the monitoring and TX feed from the cameras (requiring twice as many cable runs) or would we just run the signals through a DA before the vision mixer thus eliminating the need for these cable runs.
Other than these points the rig should not be too difficult, as such we have notified the rest of the engineers and are waiting to see whether anyone would be willing to plan and then rig this show by the 26th March.

Wednesday, 3 March 2010

Engineering - Update

There have been several developments over the past week. The first concerns the transmission equipment, this was all removed from Pres today and placed up in TV Systems for the time being. The idea is to store it here whilst the rest of the chain is being constructed, this allows easy access to the individual items of equipment. Although this seems like a good idea on the surface, it may prove to be a bad move because now there is no reference to build the new system from, whereas before if a certain item was proving to be difficult to implement it could be checked out in Pres, now it will all have to be completely assembled from scratch.

The interactive build is proceeding well and after speaking to Max last week there are several things that he needs to implement before the next stage:
The sign-up section on the Media Bugs website (where production crews will register for their "Rave Live ID Numbers") needs to have an opt out check box or drop down in it so that people have the option to sign up-to Rave Live but will not remain on the Media Bugs system after the event.
There are a lot of engineers waiting to do some coding so we need to know what needs to be done in php and MySQL so that we can get on with it.
To proceed with Brandings' "augmented reality" logo we need the Rave Live logo as a .dae (Digital Asset Exchange) file.

The OB builds are fairly stagnant at the moment because the programme producers are yet to see the space that they have to work with at the venue (the next site visit is scheduled for the 8th March). Once they have visited then we can begin to gather their equipment requirements and contact the various companies with regards to borrowing some kit off them. There was also bad news in that SiS could not provide us with an OB unit this year due to scheduling constraints. After explaining this to management the decision was taken to approach Telegenic, who kindly provided us with a second OB unit last year, to see if they would be interested again this year. We have also began to build up a contingency plan should we not be able to obtain a truck, this would be in the form of a flyaway although positioning and equipment specifications have yet to be decided.

The last major news is that Jacques and Richard have finally managed to discuss where the lines are going to be run, they are now drawing up cable schedules for the day which can be forwarded onto Matter for them to approve. Once this is done we can begin costing and budgeting for the coax runs around the venue. We have also sent an email to be forwarded onto AEG inquiring about whether or not positioning an antenna on the O2 would be possible and if opening up the various ports needed for Adobe RTSP and MySQL access would be possible, and if there would be a cost involved in doing either of these.

Thursday, 4 February 2010

Engineering - Update

Things have been progressing at a steady pace over the past few weeks. The Transmission equipment has been pulled out and reassembled on the back bench, the OB's have begun putting together system diagrams for the flyaway and the interactive team have built their server rack.

Dave (Head of Engineering), Adam (Logistics Liaison), Richard (Lines) and I went on another site visit on Jan 28th, the main reason was to investigate where the cable runs would go along with speaking again to the Matter technical staff. The main questions that had come out of the past few meetings were:

  • What is the bandwidth capabilities within Matter itself, and if we needed to open up some ports who do we need to contact.
  • In terms of DTT, what facilities are available and who else do we need to speak to.
  • What communications facilities are currently installed, can we make use of them.
It turns out that the bandwidth capabilities into and out of Matter range from 2Gb - 60Gb which is perfectly suitable for pushing the live channels onto Narrowstep. However when it comes to opening up a MySQL port, so that the local database and the website database can communicate, we need to get in contact with a higher authority within the O2.

For DTT we had previously been told that there may be some existing facilities within the O2, however the Matter staff didn't know anything about this so again they suggested getting in contact with the O2.

There is already a pre-installed communications architecture within Matter, as it stands we have been given access to one of their radio channels for use on Rave Live along with another channel which can be used to contact the Matter staff directly. This is good news as it now reduces the amount of cable runs that need to be made as hard-wired comms are probably no longer required (a redundant system will still need to be looked into).

The next stage in planning for this event now relies on commissioning, the programs should be commissioned by the end of this week, meaning that next week we can meet up with the producers with Operations and begin to get some technical requirements, once we have these the flyaway and truck engineers can then implement the requirements into their plans.